How we build a deck.
Six phases, in the order they happen, and the reason for each one. The same sequence whether the deck is freestanding or attached, on grade or elevated, around a pool or off a back door. What changes is what each phase involves on a given site.
- Phase 1Prep
- Phase 2Posts & bearing
- Phase 3Joists & blocking
- Phase 4Joist tape
- Phase 5Boards
- Phase 6Completion
Four of the six phases happen before a single deck board goes down, and five of the six are invisible once the deck is finished. A well-built deck and a badly built one look identical the day they're handed over. The difference shows up in year six.
Layout, elevations, and reading the site
Nothing gets built until the finished height is settled and the site is understood. On a deck that means finding the one elevation everything else answers to, a door threshold, a pool coping, a slab edge, and working the rest of the deck to it. It also means knowing what is already there: how the yard drains, what is buried, what is staying. Grade gets made to fit the frame, not the other way around.


Piers, ledgers, or existing slab, whichever the deck calls for
How a deck carries its load depends on the deck. Freestanding decks land on poured piers with posts set on galvanized standoff bases, which hold the bottom of the post clear of the concrete so the end grain can dry rather than wick. Decks attached to a structure get a ledger, flashed and fastened to the framing behind the sheathing, not to the siding. And where a sound concrete slab is already in place, the deck can be framed over it on anchored sleepers instead of breaking it out.


Framing the plane, and the details that disappear
The frame is where a deck is actually built. Beams and joists go in to a consistent plane, at the spacing that project requires. Spacing isn't a free choice; decking material, span, and load all drive it, and composite boards generally span less than lumber. Blocking goes in as the frame goes up, while a bay is still open and easy to square.
Two details get decided here that nobody sees afterward: a doubled joist everywhere two boards will butt together, so both boards land with full bearing, and perimeter blocking to carry a border board so field boards end on a frame instead of a raw cut edge. Anything that has to stay reachable, equipment, cleanouts, drain lines, gets framed around now.


The layer between the frame and the weather
Water doesn't come through deck boards. It comes through the gaps between them, lands on the top of the framing, and sits there, and every fastener driven through a board is a hole in the top of a joist for it to sit in. Butyl joist tape seals around the fastener and sheds the water off the side of the member instead of into it. It goes on beams and joists both, and it goes on before anything lands on them, because there's no way to add it afterward.


Surface, fasteners, and the cuts the client sees
Boards are run starting from the fixed edge, a wall, a coping, a threshold, and worked outward, so the full-width board lands where people look and any rip ends up at the outside where it reads as a border. Grooved composite boards are set with concealed fasteners: the clip seats in the groove between boards, so there are no screw heads in the walking surface and nothing to back out underfoot. Border boards go on last, covering the cut ends of the field. Anything that has to be opened later gets a framed hatch, picture-framed in the same board so it still reads as part of the pattern.


Fascia, rails and barriers, and the site put back
The open framing bay around the perimeter gets closed with fascia, which is what turns a frame into a finished edge and keeps the underside of the deck out of view. Rails, barriers, and gates go back or go in at the new elevation. Then the site gets cleared, offcuts, fasteners, packaging, and spoil, and the deck gets walked with the client.


What a deck bid is actually buying, phase by phase
When two deck bids are far apart, the difference is usually in phases two through four, the ones you can't see in the finished photos. This is what each phase decides and what it costs to get wrong.
| Phase | What gets decided | What it costs to get wrong |
|---|---|---|
| 1 · Prep | The controlling elevation and how the site drains. | A deck set to the wrong height can't be corrected without pulling boards. Water that was never planned for ends up against the structure. |
| 2 · Posts & bearing | How the deck carries its load: piers, a ledger, or an existing slab. | Posts cast into concrete wick water through the end grain. A ledger fastened to siding instead of framing is one of the most common causes of deck failure. |
| 3 · Joists & blocking | Spacing, squareness, doubled seams, border blocking, and access. | Every one of these becomes a demolition job once boards are on. Boards sharing one joist at a seam work loose. |
| 4 · Joist tape | Whether the frame is protected at every fastener penetration. | Can't be added later at any price. The frame rots from the top down, out of sight, while the surface still looks new. |
| 5 · Boards | Start point, fastener type, borders, and access hatches. | Face screws back out and catch bare feet. Boards that end on a cut edge instead of a border look unfinished from day one. |
| 6 · Completion | Fascia, barriers, and the state the site is left in. | An open framing bay collects debris and animals. A yard left dirty is what the client remembers. |
Thinking about a deck, or replacing one that's gone soft? We'll look at the site, tell you which of these phases your project actually needs, and put it in writing before anyone prices it.
Talk to Us About a DeckRelated: How we replace a roof · Carpentry · Patio covers & enclosures · Our work
This describes the sequence we work in. It is not a scope of work, a specification, or a warranty, and it does not add to or change the scope of any agreement. Which phases apply to a given project, what each one includes, and the materials and methods used are set by that project's signed estimate and contract. Site conditions, structure, and local requirements differ from property to property and are determined by an on-site assessment. The photographs are from a completed project in Central Texas and are shown as examples of each phase.